4. Delivery and warranties
The delivery of a building to its future occupants is preceded by acceptance (more precisely, by OPR: Opérations préalables à la réception, the term "acceptance" referring to the administrative act itself).
Site organization must take into account the fact that acceptance is generally global.
For example.
The company that carried out the structural work has to wait until the whole building has been completed (for example, until the carpets have been laid).
While we understand the owner's interest in this one-time reception, the consequences can be considerable for those involved.
After the waterproofing has been completed, for example, several months may pass, and the waterproofing may be punctured by subsequent parties, such as the HVAC company handling the roof.
Each trade must take steps to protect its work between...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
Delivery and warranties
Bibliography
-
GRANGE (C.) - La Loi MOP (Maîtrise d'ouvrages publics) - Un ouvrage qui permet de comprendre et d'appliquer sereinement la loi MOP. Editions Le Moniteur (2007).
-
RABATEL (M.), ESTINGOY (P.) - Prévenir les risques d'une opération de construction - Collection Méthodes, Éditions Le Moniteur (2006).
- ...
Also in our database
-
LEFEBVRE (J.-P.) - Organisation de chantiers des travaux publics - [C112v2] Construction (2009).
Software tools
AUTOCAD http://www.autodesk.fr
Directory
Manufacturers – Suppliers – Distributors (non-exhaustive list)
HAULOTTE GROUP Equipment for lifting people and loads (aerial work platforms, scissor lifts, telescopic forklifts...)
http://www.haulotte.com
ORU France Concrete batching plant
http://www.orufrance.fr/
...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!