7. Program aspect
The program aspect also plays a part in the cost of an operation. The TBM has a two-fold impact on the project schedule. On the one hand, we need to consider the time required to manufacture it, and on the other, the duration of excavation is conditioned by its speed.
The time required for design, manufacture, assembly and factory installation is generally around 12 to 14 months.
The time required for dismantling and on-site transport depends on the distance over which the TBM has to be transported. Generally speaking, it takes from 1 to 3 months.
Finally, on-site assembly time varies according to site configuration. Sometimes, the shaft in which the TBM is to be assembled is smaller than the complete TBM. In such cases, it is necessary...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
Program aspect
Bibliography
-
(1) - ANAGNOSTOU (K.) - Face stability in slurry and EPB shield tunnelling - (1996).
-
(2) - THEWES (M.), HOLLMANN (F.) - Clogging and disintegration of fines in clayey soils - (2014).
Also in our database
-
GUILLOUX (A.), LE BISSONNAIS (H.), CAHN (M.), JANIN (J.P.) - Creusement des tunnels – Méthodes de construction et géotechnique, -
Standards and norms
- Tunnelling machines – Transfer airlock – Safety regulations - NF EN 12110 - –
- Tunnel boring machines – Safety regulations - NF EN 16191 - –
Directory
Organizations – Federations – Associations (non-exhaustive list)
Association française des travaux et de l'espace souterrain (French underground works and space association)
http://www.aftes.fr
International Tunnel and Underground Space Association
http://www.ita-aites.org/
...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!