5. Power supply and quality
SCROLL TO TOP
5.1.1 Features
A distinction must be made between :
Installed capacity, the sum of all rated capacities of the applications;
the power demand, which is the power demand of all devices likely to operate simultaneously, taking into account their load and efficiency;
subscribed power, which is the power specified in the supply contract (in some cases, it may be lower than the power demand, with special tariffs applying to overruns);
pricing...