4. Reliable forecasting
After two "Remain to do" cycles, a consolidation analysis of CSR data shows that, in teams where CSR has been in place for six months, the first tangible results have been achieved.
Indeed, taking the example of our sub-project, a pilot entity in the process, forecasts have been revised several times by WP managers, following analyses of activities still to be carried out.
For the electrical bonding activities, through the "reste à faire" exercises, a re-evaluation of the distribution of the workload between the development of the different versions of the final product has been carried out, resulting in a new workload forecast model based exclusively on the "activité à faire" and not on the basis of available resources.
In the case of highly outsourced safety activities, a review of requirements has enabled us to establish a smoothing of resources...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
Reliable forecasting
Bibliography
Also in our database
-
(1) - Répertorier les coûts à suivre sur Excel : repères - [FIC 1078]...
Bibliography
Afitep, Dictionnaire du management de projet , Éditions Afnor, 5th ed. 2010
Michèle Amelot, VBA Excel 2010 - Programmer sous Excel : Macros et Langage VBA , ENI Éditions, 2010
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!