2. The monitoring reference system: the batch sheet
In a maximum of six pages, the work package description (WPD) describes all the tasks to be carried out during the project, in order to achieve the cost, time and quality objectives set for the project.
The batch header contains all the information needed to link the batch to the Work Breakdown Structure or WBS (link with the sub-project and the project) and to the Cost Breakdown Structure or CBS (description of time allocation or material purchase codes).
The document is divided into five main sections:
Assumptions: the first elements presented in the document describe the major technical, industrial and commercial assumptions made by the lot manager when drawing up the document. The scope of the lot is thus defined in accordance with the general program assumptions previously established;
The task list: this is a brief description of...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
The monitoring reference system: the batch sheet
Bibliography
Also in our database
-
(1) - Diagramme de Gantt : outil de planification - [FIC 0433]...
Bibliography
Afitep, Dictionnaire du management de projet , Éditions Afnor, 5th ed. 2010, ISBN 2124843419
Michèle Amelot: VBA Excel 2010 - Programmer sous Excel : Macros et Langage VBA , ENI Éditions, 2010, ISBN 978-2-7460-5461-5
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!