4. Scaffolding acceptance
Once the scaffolding has been erected :
the site manager checks that the scaffolding complies with
the specifications, the provisional plan and the regulations (Decree
of December 21, 2004);
acceptance is evidenced by a written document signed jointly
by the specialist installer and the user: the verification report,
before the scaffolding is put into service (or put back into service),
the contents of the report, together with the verification report
and the summary sheet drawn up by SFECE.
All signed documents must be kept on site, and a photocopied copy
kept at head office in the site file.