1. Demolding and protection
Operations carried out after the concrete has been poured are also part of the process of ensuring the durability of the structure. In this sense, since they are carried out before the concrete has reached its characteristic strength fck, they are of great importance.
This applies not only to stripping, but also to the treatments to be applied to the concrete skin.
Stripping operations can only begin once the concrete has reached sufficient strength to support the applied loads to be taken into account (hence the importance of underpinning), and no damaging deformation of the structure is to be feared.
Where there is a risk of exposure to freeze-thaw cycles, the concrete must no longer be gelling when the formwork is removed....
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
Demolding and protection
Bibliography
-
(1) - MAMILLAN (M.) - Bétonnage par temps froid et résistance au gel du béton durci. - Annales de l'ITBTP n° 477 (oct. 1989).
-
(2) - PILLARD (W.) - « La mise en œuvre » dans « Le grand livre des bétons ». - Éd. Le Moniteur (décembre 2014).
-
(3)...
Also in our database
-
DIERKENS (M.) - Béton hydraulique – Mise en œuvre – Rhéologie et maturité des bétons. -
Standards and norms
- Exécution des structures en béton : complément national à la norme NF EN 13670. - NF EN 13670/CN -
- Building work – Execution of concrete structures. - NF DTU 21 -
- Concrete surfaces and facings – Identification details. - FD P 18-503 -
- Exécution des ouvrages de génie civil en béton. - Fascicule N° 65 -
- Additives – Curing products for concrete and mortar – Definition, specifications...
Directory
Organizations – Federations – Associations (non-exhaustive list)
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!