6. Costs and deadlines
The costs indicated are only orders of magnitude, but can be used for a rough comparison of sites.
The cost of plants (including civil engineering) operating in both directions with a mean tidal range H of 5 to 8 m is probably in the order of e1,000 to e1,500/kW for a use equivalent to 3,000 h at full power. Plant investment per kW per year is therefore 0.3 to 0.5 e (Russian projects are approaching 4,000 h/year).
The economic impact of dikes varies essentially with the length of dike per km2 of basin, whose annual production in GWh is of the order of 0.7 H2 (25 GWh for 6 m). For a dike cost of e3,000/m2, i.e. e75,000/m and a dike length of 200 m per km2 of basin, the cost of the dike is e15 million per km2 of basin producing 25 million kWh/year, i.e. an investment of e0.6 per kW higher than...