4. Statutory preparation period
Once contracts have been signed, the contractor has a contractual deadline to submit his site preparation file to the project manager.
Regulations are clear on this subject, defining the obligations of the client, the prime contractor and the contractors during this period.
This preparation time is :
for public contracts, defined by the SCC or GCC, of two months (article 28);
for private contracts, defined by the SCC or the standard NF P03 0001 of three months (article 10). However, this period can be reduced to one incompressible month if the parties agree.
This period is necessary for the contractor to submit his particular health and safety plan (PPSPS). This plan...
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
Statutory preparation period
Article included in this offer
"Preparing for construction"
(
117 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Bibliography
- (1) - HAXAIRE (P.), DEBAVEYE (H.) - 170 séquences pour mener une opération de construction, - Le Moniteur, 2020.
- (2) - COUFFIGNAL (D.), BÉRAUD-GUÈNARD (S.) - Correspondancier des opérations de construction, - 2013.
Also...
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!