1. General definition
1.1 Site preparation time
A duration of 2 months appears to be the minimum desirable: this is the duration generally adopted by quality circles.
The Special Conditions of Contract (CCAP) may specify, for example, in the article concerning contractual deadlines:
Site preparation time (generally set at 2 months for projects lasting more than 6 months);
drawing up and submitting to the project manager for approval the work schedule, together with a project for site installations and temporary works;
drawing up and presenting the execution plans, calculation notes and detail studies required for work to begin. If the preparation period is not mentioned, companies...
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
General definition
Article included in this offer
"Preparing for construction"
(
117 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Bibliography
Also in our database
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!