7. Budget estimate
The company takes the "dossier de consultation des entreprises" (DCE), or the "decomposition du prix global et forfaitaire" (DPGF) file, which must be in the DCE. It extracts the values:
of the total volume of concrete (foundation, elevation...) ;
of the total floor area, including paving.
She then searches "her database" for the ratio of man-hours for all concretes.
Multiplying the total concrete ratio in cubic meters by the ratio laid in h/m3 gives an estimate of the manpower required.
SCROLL TO TOP
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
Budget estimate
Bibliography
-
(1) - HAXAIRE (P.), DEBAVEYE (H.) - 170 séquences pour mener une opération de construction, - Le Moniteur, 2020.
-
(2) - COUFFIGNAL (D.), BÉRAUD-GUÈNARD (S.) - Correspondancier des opérations de construction, - 2013.
Also in our database
Standards and norms
- Marchés privés - Cahiers types - Cahier des clauses administratives générales applicable aux travaux de bâtiment faisant l'objet de marchés privés - NF P03 0001 - Octobre 2017
Regulations
Recommendation R. 459 – Improvement of working conditions in tower cranes [obsolete, replaced by R. 495].
Directory
FFB (French Building Federation)
http://www.ffbatiment.fr
FNTP (National Federation of Public Works)
http://www.fntp.fr
CAPEB (Confederation of building craftsmen and small businesses)
http://www.capeb.fr
...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!