3. Rank and prioritize project risks and opportunities after analysis
Risk analysis is mainly characterized by the following attributes:
Root causes (uncertain event or circumstance) ;
the impact of the various possible scenarios in terms of costs, cash flow, schedule, quality, technical performance and customer satisfaction;
the action plan to mitigate the risk, with the person responsible for the action and the expected completion date;
status, with action progress ;
the risk owner, i.e. the people identified in the risk register as being responsible for carrying out controls, taking further action and monitoring specific risks.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
Rank and prioritize project risks and opportunities after analysis
Article included in this offer
"Design and engineering management"
(
337 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Bibliography
Also in our database
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!