1. Know the conventions and definitions of a PERT network
The operations to be carried out are represented on a directed graph. This representation shows all the dependencies between tasks, which will enable us to determine their earliest and latest dates, the total time required for each task, and the critical path.
The main conventions of a PERT network are as follows:
each task is symbolized by an arc, to which is associated a numerical value corresponding to its duration ;
the vertices to which the arcs lead thus correspond to stages (or events), marking the completion of one or more tasks;
each stage is identified by a sequence number, with information on the earliest ("earliest date") and latest ("latest date") dates by which it can be reached to meet the project's optimum completion date. It is represented...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
The Ultimate Scientific and Technical Reference
This article is included in
Design and engineering management
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
Know the conventions and definitions of a PERT network