1. General definition
A duration of 2 months appears to be the minimum desirable: this is the duration generally adopted by quality circles.
The Special Conditions of Contract (CCAP) may specify, for example, in the article concerning contractual deadlines:
Site preparation time (generally set at 2 months for projects lasting more than 6 months);
drawing up and submitting to the project manager for approval the work schedule, together with a project for site installations and temporary works;
drawing up and presenting the execution plans, calculation notes and detail studies required for work to begin. If the preparation period is not mentioned, companies must refuse to start work before all operations relating to this phase have been...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!
Ongoing reading
General definition
Bibliography
Also in our database
-
PAUCHET (W.) - Responsabilités en matière d'hygiène, de santé et de sécurité - [TBA 233]...
Standards and norms
- Private markets – Sample notebooks – Cahier des clauses administratives générales applicable aux travaux de bâtiment faisant l'objet de marchés privés - NF P03-001 - Octobre 2017
Regulations
Law no. 93-1418 of December 31, 1993 amending the provisions of the Labor Code applicable to building and civil engineering operations with a view to ensuring the safety and protecting the health of workers, and transposing Council of the European Communities directive no. 92-57 of June 24, 1992.
Decree no. 99-756 of August 31, 1999 on technical requirements for disabled access to public or private roadways open to public traffic,...
You do not have access to this resource.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed?
Log in!