2. Who are the Risk Manager's main contacts?
2.1 The project manager
The relationship between the risk manager and the project manager is by nature complex.
The project manager, who is responsible for the successful completion of the project, is responsible for ensuring that the risk analysis is implemented. He or she is also responsible for communication.
The Risk Manager is responsible for the operational implementation of the analyses.
Things get more complicated when we come to the conclusions of the risk analyses.
Let's imagine that the Risk Manager identifies a weighted average cost (impact x probabilities of all risks, or mathematical expectation) of €100 million, with a coverage rate (% chance of keeping to budget according...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
The Ultimate Scientific and Technical Reference
This article is included in
Design and engineering management
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
Who are the Risk Manager's main contacts?
Reference standards
FD X50-117, AFNOR, April 2003 Project management – Risk management – Project risk management
ISO 31 000NF AFNOR, January 2010 Risk management - Principles and guidelines
NF ISO 21500 NF AFNOR, October 2012, Project management guidelines
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
The Ultimate Scientific and Technical Reference