2. Update the S-curve(s) at the time of the project review to visualize progress, on time and on budget.
In preparation for the various project reviews, S-curves must be extracted from the baseline, injecting actual schedule data (time positioning and costs incurred).
This is a critical step in gathering information from project team members to the planner, in order to draw up these S-curves.
Progress at the chosen date (of the review) is calculated, and data is provided on both committed work and work still to be committed, in order to visualize the projection at the end of the business.
For each review, the planner will freeze and distribute S-curves showing the actual progress curve, the earliest budgeted curve and the latest budgeted curve. The following deliverables will be provided:
a view of the overall project ;
a view of engineering...
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
Update the S-curve(s) at the time of the project review to visualize progress, on time and on budget.
Article included in this offer
"Design and engineering management"
(
337 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!