2. Project implementation, actions taken
2.1 Project chronology
In terms of its initial objectives, the project was rolled out in the following main phases:
April to July 2009: Diagnosis with analysis of existing situation, consideration of needs and definition of recommendations, with implementation schedule;
September 2009 to September 2010: detailed definition and implementation of recommendations ;
October 2010 to May 2011: training of project managers and project referents in collaborative project management, completion of four pilot projects and implementation of the chosen software platform;
June 2011 to April 2012: assessment of the work carried out and general deployment...
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
Project implementation, actions taken
Article included in this offer
"Management and innovation engineering"
(
434 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Bibliography
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!