2. Role of each player in risk analysis
Let's take the initialization steps one by one, to highlight the role of the various players.
2.1 Defining the scope of the analysis and the reference scenario
To say that a project is likely to be a month late is meaningless if you don't know the end date and duration of the project. On a twelve-month project where planning is a key element, one month's delay represents a catastrophe. On a ten-year project, whatever the constraints, one month's delay (alone) represents a miracle.
The definition of this scenario cannot be determined by the project manager or risk manager individually.
How can we estimate a building's resistance to a reference earthquake, or the time required for operations on an assembly line,...
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
Role of each player in risk analysis
Article included in this offer
"Design and engineering management"
(
337 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!