2. Organizing the meeting
You need to plan the logistics of the kick-off meeting.
This meeting can take place in two stages, if desired: a first meeting internal to the company or consortium, and a second to be held with the customer.
The first meeting, in addition to informing and exchanging ideas with the whole team, will also serve to prepare the meeting with the customer, the first milestone in the project.
2.1 Define date, location, start and end times
To avoid any false notes, take care to :
Define and communicate the date well in advance, making sure participants are available;
Provide a venue suited to the number of participants;
...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
The Ultimate Scientific and Technical Reference
This article is included in
Design and engineering management
This offer includes:
Knowledge Base
Updated and enriched with articles validated by our scientific committees
Services
A set of exclusive tools to complement the resources
Practical Path
Operational and didactic, to guarantee the acquisition of transversal skills
Doc & Quiz
Interactive articles with quizzes, for constructive reading
Organizing the meeting
Downloadable tools
Tool
Managing a meeting (Tool ...
Exclusive to subscribers. 97% yet to be discovered!
You do not have access to this resource.
Click here to request your free trial access!
Already subscribed? Log in!
The Ultimate Scientific and Technical Reference