2. Define the budget in effect at project launch
When the project is launched and the various activities and tasks to be carried out are reviewed in detail, the budget as sold can be updated to take account of the industrial layout in place and the management of provisions.
The current budget is also updated when the customer requests an amendment, taking into account the costs associated with these requests.
The current budget must in principle be covered by an increase in the sale price of the business, which is obtained through negotiation and acceptance of contract amendments by the customer.
A new ratio (total sales price including base price and various riders / total cost) gives the new project margin.
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!
Define the budget in effect at project launch
Article included in this offer
"Design and engineering management"
(
337 articles
)
Updated and enriched with articles validated by our scientific committees
A set of exclusive tools to complement the resources
Exclusive to subscribers. 97% yet to be discovered!
Already subscribed? Log in!