3. Interactions between MRP, JIT and TQM

The philosophy behind push-flow systems is to focus on planning to simplify workshop management. The general diagram of the method shows this quite clearly. There are many planning modules for a single workshop management module.

If planning is well carried out (at all levels: SOP, MPS, CBN), then workshop management should be simpler. Shop floor management can be computerized, but if the planning process has been well carried out and the production process is not too complex, it is possible to schedule work on the machines without software. In this case, scheduling will be carried out by setting up a Kanban loop to ensure that workshops operate autonomously according to demand (pull flow).

It should be noted that the use of Kanban to manage a workshop is beneficial for the company (less stock, high reactivity, empowerment of operators),...

You do not have access to this resource.
Logo Techniques de l'Ingenieur

Exclusive to subscribers. 97% yet to be discovered!

You do not have access to this resource. Click here to request your free trial access!

Already subscribed?


Ongoing reading
Interactions between MRP, JIT and TQM

Article included in this offer

"Logistics and Supply Chain"

( 85 articles )

Complete knowledge base

Updated and enriched with articles validated by our scientific committees

Services

A set of exclusive tools to complement the resources

View offer details

Contenus associés

Sur le même sujet

Veille personnalisée : Inscrivez-vous !

Dans les ressources documentaires

Planification avancée - L’apport des Advanced Planning Systems

Les systèmes MRP ont évolué à la fin des années 1990 vers des modules «  Advanced Planning Systems  ...

Prévisions systémiques dans la supply chain globale

De plus en plus, les entreprises doivent malgré les attaques financières, spéculatives et économiques, se...

Enjeux de la chaîne logistique – Supply Chain management

Le management de la chaîne logistique, aussi appelé supply Chain management, est un enjeu stratégique maj...

Benchmarking de la supply chain

Le Benchmarking de la supply Chain permet aux entreprises de communiquer leurs problématiques, de mesurer...

WhitePaper
27 January 2015
Robotisation, mode d'emploi

Comment mettre en place avec succès un projet de robotisation dans son entreprise ? Approche, démarche, conseils...

Tous les livres blancs
Toutes les actualités
Contact us