7. Rules of use

  • Commissioning

If the crane (or gantry crane) is large enough to be transported fully assembled (see road jig), it will be installed in a single operation. In all other cases, the equipment will have to be assembled on the ground before it can be installed, so always provide a clear area for this preparation. This operation requires lifting equipment ranging from a simple hoist installed on the roof structure to a truck-mounted or self-loading crane weighing several tons, so you need to provide access for these machines.

  • Maintenance and operating manuals

Each bridge or gantry must be accompanied by an instruction manual giving the following information:

  • instructions for commissioning: installation, assembly,...

You do not have access to this resource.
Logo Techniques de l'Ingenieur

Exclusive to subscribers. 97% yet to be discovered!

You do not have access to this resource. Click here to request your free trial access!

Already subscribed?


Article included in this offer

"Logistics and Supply Chain"

( 85 articles )

Complete knowledge base

Updated and enriched with articles validated by our scientific committees

Services

A set of exclusive tools to complement the resources

View offer details
WhitePaper
27 March 2015
Les bonnes pratiques de laboratoire

Les « bonnes pratiques de laboratoire », également appelées BPL, ont pour objectif d\'empêcher un nouveau scandale et sont appliquées au niveau mondial.

WhitePaper
4 December 2018
Caméra thermique : FLIRGFx320

Caméra infrarouge pour la détection des gaz à sécurité intrinsèque. Description produit de deux pages

Tous les livres blancs
Article Anomalie de cuve : l'avenir de l'EPR menacé ?
16 April 2015
Anomalie de cuve : l'avenir de l'EPR menacé ?

Début avril, Areva a notifié à l’Autorité de Sûreté du Nucléaire française (ASN) une anomalie de composition de l'acier dans certaines zones du couvercle et du ...

Toutes les actualités
Toutes les conférences en ligne
Contact us